Metal roof replacement: replacing shingles with standing seam

Many of the metal roofs we install replace a worn-out asphalt roof. Here is how the decision gets made, what happens on each day, and what changes at every detail on the way.

The short answer

Replacing an asphalt roof with a standing seam metal roof usually takes 3 to 6 working days on site, and the first decision is whether to tear off the shingles or strap over them, which only works over one sound layer on dry, flat roof boards. CGD Roofing, based in Barrie, inspects the attic and the roof before quoting, forms the panels on your driveway, and does this work across Simcoe County, Muskoka, Grey Bruce, the Kawarthas and York Region. You get a written specification before you commit, never a price over the phone.

Tear-off or strap-over: the first decision on any metal roof replacement

There are two ways to replace shingles with a metal roof. A tear-off strips the asphalt down to the roof boards, repairs or replaces any boards that are soft, and builds the new roof from there. A strap-over leaves one layer of shingles in place, fixes horizontal strapping through them into the structure, and installs the panels on that strapping, which leaves a ventilated air space under the metal. That strapped assembly is our Gold package, and on the right house it is the better roof, not the budget one.

The right house means one layer of shingles, roof boards that are dry and solid everywhere, no history of moisture in the attic, and roof planes that are reasonably true. Two layers, a soft spot underfoot, staining on the underside of the boards or a visible sag all mean a tear-off. We make that call from evidence gathered on your roof and in your attic, and the quote says what we found. If the evidence points to the more expensive option, that is what the quote will say.

What we inspect before quoting a replacement

A replacement quote is only as good as the inspection behind it. Before we price anything we look at the parts of the house the new roof will depend on, using a drone survey, a walk of the roof where it is safe, and a look in the attic.

  • The underside of the roof boards from the attic: staining, mould bloom, rusted nail tips, daylight.
  • Layer count at a rake edge, and any soft or spongy areas on the roof itself.
  • Whether each plane is true, or whether there is a dip, wave or sagging ridge that metal would show.
  • Soffit intake and existing roof vents, including insulation packed into the eaves.
  • Chimney condition: the crown, the mortar joints and how the old flashing was let into the brick.
  • Skylight age and type, plumbing stacks, exhaust fan outlets and any electrical mast through the roof.
  • Eavestrough and fascia condition, because a new roof is the cheapest time to deal with both.

What 3 to 6 days on site actually look like

Day one is set-up and protection. Bins and the roll former go on the driveway, tarps go over gardens and against the walls, and work starts on the first planes. On a tear-off, a careful contractor only opens as much roof as can be dried in with underlayment that same day. On a strap-over, the strapping and underlayment go down plane by plane instead.

The middle days are the roof itself. Eave trim and drip edge go on first, valleys are built before the panels that meet them, and panels are formed on site to the exact length of each slope, one continuous piece from ridge to eave. Chimney, wall and skylight flashings are bent on our brake as each one is reached rather than ordered from a catalogue.

The last day is ridge, final trim, snow retention where it was specified, and cleanup, including a magnet sweep of the lawn, beds and driveway. Simple roofs land at the short end of the range. Steep pitches, lots of dormers and valleys, a tear-off with board replacement, or a run of bad weather push toward the long end.

What changes at chimneys, valleys, vents and skylights

Shingles and metal handle details differently, and a replacement is where most of the long-term quality is won or lost. Every existing flashing is replaced rather than reused.

  • Chimneys get new step and counterflashing bent to fit, and a wide chimney gets a cricket on the uphill side so water and snow are split around it instead of piling against the brick.
  • Valleys are rebuilt as open metal valleys with the panel ends hemmed, not lapped, so nothing relies on sealant in the place where two roofs pour into one.
  • Plumbing vents get new flexible boots made for metal, positioned in the flat of a panel rather than across a seam.
  • Box vents usually come out in favour of a continuous ridge vent, which only works if the soffit intake is open.
  • Skylights near the end of their life should be replaced during the roof, not after it, because re-flashing a skylight later means disturbing the new panels around it.

Ventilation and ice dams: fix them while the roof is open

A new metal roof does not cure an ice dam caused by heat escaping into the attic. Ice dams form when warm air melts snow higher up the slope and the water refreezes at the cold eave. Metal helps because snow slides sooner, but the cause is usually blocked soffits, missing baffles, bathroom fans venting into the attic, or gaps around light fixtures and the attic hatch.

A replacement is the one time the eaves are fully open, so it is the time to restore intake, fit baffles where insulation has slumped into the soffit, and install a ridge vent that matches. High-temperature ice and water membrane goes at the eaves and valleys, and on our Gold package it runs past the code minimum. If the attic tells us the problem is air sealing inside the house, we will say so, because that part is not a roofing job.

Replacing an old exposed-fastener metal roof

Not every replacement starts with shingles. A lot of houses and cottages around Simcoe County and Muskoka carry screw-down metal from decades ago that has reached its second or third round of leaking washers. Sometimes a re-screw is still the right answer, and our metal roof repair page covers that. When the panels are rusting through, the laps leak on a shallow pitch, or the roof has been re-screwed before and the holes are worn out, replacement makes more sense.

In most cases the old ribbed panels come off. They do not give a flat plane to build on, and the fastener holes and any rust underneath need to be seen. Many older screw-down roofs were fixed to strapping with no solid boards at all, so the replacement often starts with new sheathing before the underlayment and standing seam go on.

Permits and the paperwork

Whether a re-roof needs a building permit depends on the municipality and on what is changing. Replacing a covering like for like is often treated differently from replacing roof boards, altering structure or changing the roof shape, and the rules are not the same in every town we work in. Call the building department before work starts. If the house has a heritage designation or sits in a heritage district, speak to the heritage planner as well, since material and colour can be part of that conversation. Your insurer will also want to know the roof has been replaced, so keep the specification and the final invoice together.

What a good metal roof replacement quote should list

  • Tear-off or strap-over, and the evidence that decision was based on.
  • How soft or damaged roof boards will be handled and priced if they are found.
  • Panel gauge, seam type, finish system and colour.
  • Underlayment type, and how far ice and water membrane runs at the eaves and valleys.
  • Every flashing that will be replaced: chimneys, walls, valleys, vents and skylights.
  • How the roof will be ventilated, intake and exhaust both.
  • Snow retention: whether it is included, and where it goes.
  • Cleanup, disposal and the magnet sweep.
  • The workmanship warranty and the finish warranty, in writing, with exclusions.

How we build it

Three levels of assembly, quoted from a measured survey, never a rate card. We will tell you which one your building needs, including when that is the simplest one.

Silver

Direct installation

Panels formed on site and installed over sound existing roof boards. The straightforward option when the structure underneath is already in good shape.

  • 1" mechanical lock standing seam, roll-formed on site
  • 26 gauge steel, standard colour range
  • Synthetic underlayment
  • Standard ridge, eave and gable flashings
  • Full site cleanup and magnet sweep

Best for: Sound decks, simple rooflines, budget-led projects

Quote the Silver system
Homeowner favourite

Gold

Strapped & ventilated

Adds a strapped substrate that creates a ventilated cavity under the panel, the assembly that actually addresses ice damming rather than hiding it.

  • Everything in Silver
  • Strapping system for a ventilated air cavity
  • High-temperature ice & water shield, past code minimum
  • Choice of 24 or 26 gauge steel
  • Snow retention assessment mapped to your roof

Best for: Most Ontario homes. The one we would put on our own houses

Quote the Gold system

Platinum

Architectural grade

Full architectural detailing in 24 gauge with a PVDF finish. For heritage homes, custom builds, and anything where the roof is a design element.

  • Everything in Gold
  • 24 gauge steel with PVDF (Kynar 500) finish
  • Custom chimney caps, coping and box eavestrough
  • Double-lock 180° seams throughout
  • Concealed-fastener detailing at every transition

Best for: Chalets, heritage homes, complex or highly visible rooflines

Quote the Platinum system

Every project is quoted from a site visit or drone survey, roof complexity, tear-off versus overlay, gauge, finish and access all move the number, and none of them can be assessed from a postcode.

Metal Roof Replacement questions

How long does it take to replace a roof with metal?

A typical house re-roof with standing seam metal takes 3 to 6 working days on site. A simple gable roof strapped over one layer of shingles sits at the short end. Steep pitches, many dormers and valleys, a full tear-off with replacement of soft roof boards, or poor weather push it toward the long end.

Can a metal roof go over my existing shingles?

Only over one layer of shingles on roof boards that are dry, solid and reasonably flat, with no sign of moisture in the attic. In that case strapping is fixed through the shingles and the metal goes on the strapping, creating a ventilated air space. Two layers, soft spots, attic staining or a sagging plane all mean the shingles should come off first.

Do I need a permit to replace my roof with metal in Ontario?

It depends on the municipality and the scope of work. Replacing a roof covering is often treated differently from replacing roof boards or changing the structure, and requirements vary from town to town. Check with your local building department before work starts, and with the heritage planner if the property is designated.

Will a new metal roof stop ice dams?

It helps, because snow slides off metal sooner, but it does not fix the cause. Ice dams come from heat escaping into the attic and melting snow that refreezes at the eave. The lasting fix is open soffit intake, a matching ridge vent, high-temperature membrane at the eaves, and air sealing inside the house where warm air is leaking into the attic.

Can you replace an old screw-down metal roof with standing seam?

Yes. The old exposed-fastener panels usually come off so the condition underneath can be checked. Older screw-down roofs were often fastened to strapping with no solid boards, so new sheathing may go on before the underlayment and the standing seam panels.

How much does it cost to replace a roof with metal in Ontario?

It depends on the measured roof area, pitch, complexity, tear-off versus strap-over, gauge, finish and access. CGD Roofing does not quote from a phone call or publish a rate. The cost guides on our blog explain what drives the price, the online range tool on the quote page gives a whole-project range in about 90 seconds, and a site visit or drone survey produces a written, measured quote.

Worth reading first

Where we do this work

Other metal roofing services

Get a real number on your roof.

We quote from measured drawings or a drone survey, never from a phone call. Tell us where you are and what you have, and we will tell you honestly whether we are the right fit.

The online range takes about 90 seconds and no phone call.